           The accumulated downtime of each subsystem is shown in Fig. 5, with 99.73 h in total. Together with the trip
           events listed in Table 5, it is shown that some trip events resulted in a long downtime. For example, a single cryo-  Facility Status
           genic event took about 6 h to effect a system recovery; this instance indicates the importance of great reliability
           of these critical subsystems. (Reported by Chang-Hor Kuo)






 ACTIVITY REPORT  2016
































           Fig. 4:  An event of partial beam loss recorded with a rapid diagnostic system, in which an abnormal timing trigger for kicker waveform
                was caught.

































                    Fig. 5:  Downtime of each subsystem in 2016.