Page 70 - 同步輻射-全
P. 70

068





             Table 4: Monthly beam stability index of TLS                      Downtime and failure
                                                                               analysis
             Month      < 0.1%    < 0.2%      Month      < 0.1%    < 0.2%                                                                                                                                                                 Facility Status
                                                                               In 2016, in total there were 55
             January    95.3%      99.9%       July      97.0%     99.9%       beam trips with an average recov-

            February    98.0%      99.9%      August     95.9%     99.8%       ery time 1.8 h for each trip event.
                                                                               As Table 5 illustrates, 11 beam
             March      99.0%      99.9%    September     N/A       N/A
                                                                               trips were attributed to others,
              April     99.5%      99.9%     October     98.1%     99.8%       including partial beam loss, sag of
     ACTIVITY REPORT  2016
              May       97.1%     100.0%    November     97.5%     99.8%       electric power and earthquakes;
                                                                               5 faults to power supplies of the
              June      97.0%      99.9%    December     97.7%     99.8%
                                                                               magnets, nine faults to SC mag-
                                                                               nets and six failures of the injec-
                                                                               tion system, including incorrect fir-
                                                                               ing of kickers. A partial beam loss
                                                                               during injection in top-up opera-
                                                                               tion was still a major problem of
                                                                               TLS, as before, as the RF protection
                                                                               loop detected an abnormal power
                                                                               change and then activated the
                                                                               interlock to trip the RF system so
                                                                               as consequently to kill the stored
                                                                               beam. Many tiny fluctuations and
                                                                               rapid abnormal behaviors of in-
                                                                               jection-related units could cause a
                                                                               partial beam loss; a diagnostic sys-
                                                                               tem with a rapid transient record-
                                                                               er was hence built to identify the
                                                                               occasional event. Figure 4 shows
                                                                               a partial beam-loss event with an
                                                                               abnormal timing trigger wave-
          Fig. 3: Quarterly beam performance of TLS for user time in 2015 and 2016.  form from a pulsed power supply
                                                                               of the kicker. The main board of
                                                                               the kicker controller was then
                                                                               replaced as an attempt to solve
            Table 5: Summary of major trip events                              this trigger problem. The rapid
          Subsystem    Event                                    Beam trips     diagnostic system assisted greatly
             Others    Partial beam loss without a clear reason      6         to decrease the partial beam-loss
             Others    Sag of electric power                         2         events, but unclear consequenc-
             Others    Earthquake                                    3         es still occurred. Further effort is
           Power supply Power supply of sextuple magnet failure      3         required to improve this system
           Power supply Power supply of corrector magnet failure     8         and to examine the consequences
           Power supply Power supply of quadrupole magnet failure    3         and reasons.
                       Transport line power supply of dipole magnet fail,
           Power supply                                              1         Table 5 shows clearly also that
                       lower than user beam definition.
             Magnet    SC magnet fail                                9         some components of the subsys-
             Injector  Incorrect firing of kickers                   5         tems, such as power supply and
              Linac    Aged klystron modulator power supply relay    1         injection system, are approaching
                                                                               their lifetimes. This occurrence
                                                                               affects all subsystems of TLS after
                                                                               construction nearly three decades
          RF system:                                                           ago. As some components are
          • Beam processing on the SRF module was applied by adjusting various   even unavailable any more, prepa-
           tuning angles with large beam currents after a scheduled shutdown pe-  ration work such as to modify the
           riod, to increase the reliability of the RF system as a vacuum burst event   interfaces in advance at scheduled
           in a SRF module was eliminated.                                     shut-down periods is critical to
                                                                               upgrade the old components with
                                                                               new modules before failure.
   65   66   67   68   69   70   71   72   73   74   75